African Integrated High Speed Railway Network

Background

The economic development of the African continent and its ability to unlock its trade potential is strongly tied up with the available transport infrastructure; and in particular, the reliability of its railways. Freight costs in Africa are high and are disproportionately higher than other regions of the world. This limits global competitiveness, intra-African trade and consumer buying power.

African railways while predominantly being a legacy of transportation corridors for transferring commodities from the interior to coastal ports, are in today’s assessment of need, sparse -see Table 1. Sixteen countries have no railway lines and many of the existing networks are in significant need of an upgrade and are operated by outdated and bureaucratic management with limited commercial viability and marketing.

Table 1 : Comparative Railway Densities – source from African Union High Speed Railway Network report.

While particular circumstances contribute to Africa’s predicament; such as challenging and diverse geography; population density; and its record on social stability and governance; there remains an obvious infrastructure gap in comparison to a world average railway density.

The vision

The African Union (AU), a continental body of 55 member states that promotes peaceful development and unity across the African countries, has set a Programme for Infrastructure Development (PIDA) framework, in collaboration with other partners. This includes the development of the Agenda 2063  Agenda 2063 Integrated High Speed Rail Network – to address the infrastructure gap in Africa.

As one of the flagship projects of the Agenda 2063, this network stands as the commendable forward-thinking project that, although presenting many challenges, brings together Union members to establish long-term goals prioritising railway links. Its aim is:-

[…] to connect all African capitals and commercial centres through an African High-Speed Train Network thereby facilitating the movement of goods, factor services and people. The increased connectivity by rail also aims to reduce transport costs and relieve congestion of current and future systems.

African Union

Publicly available details on the Integrated High Speed Rail Network are limited and this PIDA video has some discrepancies from the AU report. We at Capiro understand that the draft vision between the AU and China, one of the project partners, is still under consultation with preliminary routes and pre-feasibility studies to be progressed.

Nonetheless, PIDA has defined 11 African Regional Transport Infrastructure Network (ARTIN) corridors needing railway updates or entirely new rail lines as soon as possible to meet projected 2040 demands.

Table 2: PIDA Railway Construction and Modernisation Programme for ARTIN – source from African Union High Speed Railway Network report.

At Capiro we were unable to locate a map which outlined the extent of the railways defined in Table 2, and information on how these corridors will align with the wider high-speed network.

Challenges ahead

The implementation of these projects raises a number of important questions on the applicable timescales and technical specifications for a unified and interoperable route:-

  • What is the adopted speed?  High speed rail often adopts speeds above 250km/h for new lines, or above 200km/h when adopted on existing lines. The only high-speed railway line in Africa is located in Morocco and connects Tangier to Casablanca. It is able to reach 360km/h. We expect the Integrated High Speed Rail Network to adopt the definition of above 200km/h, with options on the method to power these trains across the route varying between diesel, electric or dual system. However, where electrification should be the target, outlining a suitable power supply infrastructure with standard requirements throughout the network is paramount.
  • Which rail gauge will be adopted? African railways vary between metric gauge (1000mm wide) which covers 19.2% of existing track; Cape Gauge (1067mm wide) which covers 61.3% of existing track; Standard gauge (1435mm wide) which covers 14.5% of existing track; and six other gauges which cover the remaining 5% of existing track. It is noted that there are train vehicles that can cope with dual gauge, or dual gauge track sleepers, but for a suitable long-term development, a standard gauge should be adopted.
  • How will it be operated and governed?  Will a continental group under the AU manage and/or set the standards to be applied throughout? A single interoperable signalling system is the approach taken by the European Union Agency for Railways (ERA) with its European Rail Traffic Management system (ERTMS). However existing railways in Africa have been using both the Chinese Train Control System (CTCS) and the European Train Control system (ETCS) leading to non-interoperable sections of railways such as: Ethiopia’s Awash-Weldiya on ETCS and Addis-Ababa to Djibouti on CTCS. For successful operation of the Integrated High Speed Railway Network, a joined up approach is required.

These are questions which we at Capiro are looking to investigate.  A successful and uninterrupted journey from Cape to Cairo will have to fully consider and address these issues and be aligned, if not otherwise part of, the African Integrated High Speed Railway Network.


Kazungula: A case study in multilateral co-operation on infrastructure

In 2011 the African Development Bank (ADB) concluded that in order to enhance the economic integration of the Southern African Development Community (SADC) – A region that represents 40% of sub-Saharan GDP – a key piece of infrastructure had to be built at the fairly nondescript town of Kazungula.


Location of Kazungula Bridge

Some Context

Located approximately 60km west of the famous Victoria Falls, the location of the Zambian town of Kazungula is unremarkable save for the following fact: the 4 national borders of Namibia, Botswana, Zambia and Zimbabwe meet at a single point in the middle of the might Zambezi River. In the days when the Zambezi was thought to be navigable (and therefore able to link the rich African interior to the Indian Ocean), access to it was considered vital. Thus came about the curious wedge of Namibia (then known as German Southwest Africa) between Angola (then a Portuguese colony) and Zimbabwe (what was then a British territory).

The Zambezi is not navigable along its entire length (we draw your attention to the Victoria Falls), but Kazungula nonetheless remains a strategic crossing point due to its position in the north-south trading corridor through the SADC region. A ferry service currently acts as a border crossing between Zambia and Botswana, but it is notoriously inefficient. According to ADB, commercial traffic can take up to 10 days to clear immigration. However, this is mercifully more expedient for tourists who are on their way to Chobe National Park in Botswana, which is bewilderingly rich in wildlife.


The bridge under construction

The Corridor

The ‘North-South Corridor’ is a key trade route identified by ADF. Approximately 2800km long, it stretches from the mining region of Lubumbashi in the Democratic Republic of the Congo to the port city of Durban in South Africa. Along the way it passes though the Copperbelt (Zambia’s industrial heartland) and Gaborone, the capital of Botswana. With spill over effects, corridor further integrates Namibia, Zimbabwe, Lesotho and Eswatini.

This north-south corridor is primarily road-based and the Kazungula crossing point is a critical bottleneck that prevents the flow of goods due to the inefficient infrastructure. An improved crossing not only provides the opportunity to increase the capacity and speed of transit, but it also introduces an alternative mobility mode: railway transportation.


The Bridge

At the time of writing, the project is well and truly on its way to completion. The most obvious physical aspect of bridge is the curved route it takes across the Zambezi. The mystery dissolves once the national boundaries are revealed. We speculate that the curve allows the bridge to cross through the opening in the Zambian border, which is only 150m, formed by the Botswanan border. This avoids crossing Zimbabwean airspace – and the obvious complications that would accompany a tripartite agreement.

Here are some key data for the project due to open in late 2020:

  • It is a 925m long, 18.5m wide viaduct across the Zambezi River
  • Design type: extradose cable stayed bridge
  • Longest span: 129m
  • Number of road lanes: 2
  • Railway tracks: 1, narrow gauge 1.067m
  • US$260 million capital cost
  • Main contractor Daewoo of South Korea
  • One-stop border crossing facility located on the Zambian side

Aerial view
A strategic crossing over the Zambezi River

Financing the Project

As the Victoria Falls Bridge demonstrates, crossing the Zambezi is no small feat. And whilst Botswana is a middle-income economy, the project would be an extremely costly undertaking (approximately 1% of Zambian GDP).

Recognising the potential regional impact of the crossing, the ADF through its African Development Fund (ADF), the Japan International Cooperation Agency (JICA ) and the EU-Africa Infrastructure Trust Fund (ITF) provided a loan to the governments of Zambia and Botswana amounting to 90.8% of capital expenditure (see table), 1.8%  presenting a grant by ITF for the establishment of the Kazungula Bridge Authority that will manage the asset.


JICA57.5%
ADF31.5%
Zambian Government5.2%
Botswanan Government4.0%
ITF Grant*1.8%
* Not a loan
Source: ADF Project Appraisal, 2011
Kazungula Bridge Financing Contribution

Governance

The loans from ADF and JICA are zero interest (we at Capiro! note with glee), with a tenor period of 50 years inclusive of a 10 year grace period. The executing agency for the project is a combination of the Zambian and Botswanan road authorities. Adjusting for the usual capriciousness of projects, from what we can observe the governance of the project is meeting its objectives and the crossing is expected to open late 2020.

Once operational, the bridge will be managed by the Kazungula Bridge Authority, which will be set-up using the ITF grant. In effect, the project will be run similar to other trans-boundary projects that are essential for landlocked countries such as Botswana and Zambia (especially the latter). Notable examples are the Tazara Railway and Kariba Hydro Electric Dam.


Economic Sustainability

Delivery of the project is one thing, ensuring that it survives to fulfil its purpose is quite another. An anecdotal survey of major infrastructure across the continent paints a dismal picture of asset management. Simply put, adequate maintenance regimes aren’t in place. The Kariba Dam down the river is a fine example of this phenomenon. Therefore economic sustainability was placed at the heart of this project.

Evaluation of economic sustainability was based on the economic internal rate of return (EIRR) and the net present value of toll revenue. With an assumed opportunity cost in Zambia of 12%, the base case of the project yielded an EIRR of 23% and a benefit-cost ratio of 2.34. Even with an increase in costs of 20% and reduction in benefits of 20%, an EIRR of 17.5% and benefit-cost ratio of 1.56 provided a convincing case for financing the project. The opex (cost of operating the bridge) was intended to be covered by the toll revenue. A conservative assumption of 2.5% annual growth in traffic and 5% annual growth in opex were assumed and found to be covered by projected toll revenue.

We find it interesting that this was based purely on the current modes of transport serviced by the ferry crossing. Therefore this did not account for rail mobility – such as Capiro! – or even the commercialisation of lands adjacent to the crossing (i.e. renting land near the bridge). This means that the bridge should more than be able to pay for itself!


Implication for Cape to Cairo

Achieving the vision of connecting Cape Town to Cairo by rail, uninterrupted, will require the construction of strategic assets similar to the Kazungula Bridge. This project is an excellent example of how assets with broad regional – or continental – importance can be delivered: Through the concerted effort of the right stakeholders, sound economic rationale and execution capability. (We will aim to demonstrate this through a feasibility study we will conduct.)

Of course, what this project does mean is that another potential route opens up for the Cape to Cairo route – via Botswana! With the Kazungula crossing, it appears as though the governments have committed to constructing a railway line between Livingstone (in Zambia) and Mosete (Botswana). A very exciting prospect indeed!

The main concern we at Capiro! have is that the railway track on the Kazungula Bridge will be narrow gauge rather than the standard gauge. One of the greatest obstacles to the vision is interoperability, which on an obvious level requires the tracks to be the same width. One step at a time…

In the meantime, this corner of Africa looks set to become a strategic economic asset with regional importance. It will cease to be a quick of the past and instead become a link to power future economic grown in the SADC region.